2018 Street Maintenance Program

Updates on the City's annual street maintenance program.

View All Posts

Aug 27

2018 Street Maintenance Program Shifts to Ridge Drive and East Taylor Street

Posted on August 27, 2018 at 12:14 PM by Patrick DiDiana

The City Contractor has completed Phase I of the 2018 Street Maintenance Program, the Elwood Neighborhood, and now will simultaneously begin Phases II and III. 

Phase II work tentatively scheduled for maintenance to begin on September 5, includes the streets listed below.  Contractors will begin to stage construction equipment on August 30.  Maintenance includes upgraded ADA compliant crosswalks, spot curb repairs, and resurfacing.  

Street  From To
East Taylor  7th Street   Maplewood
Maplewood  Taylor Street   Pavement Change
 South 11th Street Taylor Street   Pavement Change

Phase III work on Ridge Drive from Bayfield Drive to First Street is tentatively scheduled to begin on September 4.  The staging of construction equipment will also begin on August 30. 

The timelines below describe Phases II and III work. 

Phase II Graphic 
Phase III Graphic

Timeline dates are subject to change due to weather.  Curran has targeted October 9, 2018, as the end date for all work in these areas.