IMG_0973

2018 Street Maintenance Program

Updates on the City's annual street maintenance program.

View All Posts

Jul 25

Ellwood Neighborhood Update

Posted on July 25, 2018 at 7:40 AM by Patrick DiDiana

Street maintenance continues to progress in the Ellwood Neighboord.  Since last week, contractors have worked to remove curbs and sidewalk ramps.

IMG_0136
This week, contractors began removing driveway approaches marked for repair.  Residents with driveway approaches scheduled for repair will not have access to their driveway for a minimum of five (5) days. The extended period will allow contractors to form, pour, and cure the new concrete driveway approach.  

IMG_0139

Contractors have also started pouring curbs and sidewalk ramps throughout the neighborhood.  Concrete pouring and driveway approach work will continue into the following week.  As this work concludes, the contractors will begin to prepare the streets for repaving.
  
IMG_0143