2018 Street Maintenance Program

Updates on the City's annual street maintenance program.

View All Posts

Jul 09

2018 Street Maintenance Program Begins July 11, 2018

Posted on July 9, 2018 at 4:34 PM by Patrick DiDiana

On July 11, 2018, Curran Contracting Company (Curran) will begin the 2018 Street Maintenance Program.  This year’s program will focus on three geographic areas throughout the City and conclude with a citywide crack-filling schedule. 

The table below lists the streets that comprise the scheduled work areas for the Ellwood Neighborhood.  Constructions crews will work in three phases to replace damaged curbs, sidewalks, driveway approaches, and repave streets. 

Street

From

To

College Avenue

John Street

Linden Place

August Avenue

College Avenue

First Street

Linden Place

Miller Avenue

College Avenue

Miller Avenue

Woodley Avenue

Linden Place

Miller Court

Linden Place

East End

Park Avenue

College Avenue

Thornbrook Road

Rolfe Road

Woodley Avenue

Linden Place

Thornbrook Road

Park Avenue

East End

Woodley Avenue

North End

Augusta Avenue


The timeline pictured below describes each phase of work for the Ellwood Neighborhood.  Timeline dates for the Ellwood Neighborhood are subject to change due to weather.  Curran has targeted August 16, 2018, as the end date for all work in the Ellwood Neighborhood.  


Ellwood Chart_002